Below you will see the calendar for the 2012B semester (plus a little
more) showing the pODI activities from the readiness and safety review
(July 12) through shipping, installation, engineering verification and
commissioning. The dates colored yellow on the calendar show when other
instruments will be in use. The dates colored blue have been set aside
for preliminary shared risk observations by the WIYN partner scientists
who have helped with commissioning. Regular shared risk will start in
March 2013.